A final layer of stone has been laid to the new section of road to the west of Tollemache Road ahead of surfacing work to take place next spring.Stone and rubble continues to arrive on site as the two new roundabouts are created. Last week 10,000 tonnes arrived on site and a further 1,500 tonnes excavated from the field next to the A1. Across the site drainage and utility work continues as does formation of the banks. Fitzgerald Engineering is the contractor for this first phase of work which entails the building of a roundabout off the B1174 and a 490m stretch of road along Tollemache Road culminating in a second roundabout.

0 Comments

Submit a Comment

Your email address will not be published. Required fields are marked *